Design, manufacturing, delivery, installation and commissioning of a cryogenic supply system to supply liquid hydrogen from a tank to up to four (4) test positions. • Pipeline Types: o Cryogenic Pipeline: Vacuum-insulated, DN40 PN16, approx. 110m in length o Cryogenic Transfer Pi
Lot 1: Liquid Hydrogen Supply (LH2) for P8 Test Bench at Test Site DLR Lampoldshausen: Delivery of LH2 to the P8 test bench at Test Site DLR Lampoldshausen in several batches for the period January 2026 – December 2026. The amount of delivered LH2 to DLR Lampoldshausen P8 is esti
TED
Design, manufacturing, delivery, installation and commissioning of process control system for a hydrogen supply system: PCS: • Process control system (Beckhoff) based on the existing process control system of a comparable test bench o remote I/O o PLC o Industrial PC o Network (E
TED
Design, manufacturing, delivery, installation and commissioning of a flare.