US-TX ESBDUnited States
OLD ALICE ROAD – PROJECT (CSJ: 0921-06-290, etc.)
The work under this Contract shall be Substantially Complete Four Hundred and Eighty (480) working days after the initial notice to proceed (NTP). The Contractor will be allowed up to an additional ten (10) calendar days for Final Acceptance. The contract time includes the mobili