EKFB NC2A - Transport and installation of precast tunnel segments
Purchaser
Eiffage Kier JV HS2 Main Civils Works, Lots C2 & C3
Country
United Kingdom
Published
8 Oct 2025
Closing date
Not listed
Source ID
Docs found
—
Save this notice and create a tender alert for similar public opportunities.
- Create one free tender alert.
- See a short explanation of why each tender matches.
- Upgrade later when you want help planning and writing the bid.
Summary
The Wendover Green Tunnel consists of five pre-cast concrete segments but is intersected by two bridges negating the ability to place the tunnel sections by traditional crane. An alternative solution anticipated using an SPMT (Self-Propelled Modular Transporter). Product weights are dividing wall 43.6tonne, arch wall 37.5 tonne, arch roof 19tonne. The arch roof sections are lifted to approx. 12m high. The tunnel segments have been procured and are delivered to site on trailers.